This is an archived article and the information in the article may be outdated. Please look at the time stamp on the story to see when it was last updated.

MEMPHIS, Tenn. — Lane closures for a major construction project at the Interstate 55/Crump Boulevard interchange will begin June 6, TDOT said.

The I-55 southbound ramp will be down to one lane. One lane, and the shoulder, of I-55 south will be closed from 8 p.m. to 6 p.m. beginning that Monday. Two southbound lanes of the interstate will remain open.

The temporary closures are expected to last eight months.

The $141 million project will build new through-traffic lanes for I-55, eliminating the need for the slow-moving cloverleaf ramps at that interchange.

A new roundabout will be built at Crump Boulevard. The project also includes repairs to the I-55 river bridge deck.

The entire project is expected to be complete in 2025, TDOT has said.